Friday, June 7, 2013
Today I finished installing all the door knobs and door pulls. Janice finished cleaning all the windows and installed some of the screens. Tomorrow we'll finish installing the screens and reserve the buffer for one last floor buffing and sealing on Monday. Tomorrow we also have to make copies of the floor plan for the Williamson County tax folks. We have an appointment with them on Tuesday.
Trico, the propane company providing our service, came by and fixed the stove. It's up and running. They tested the system and everything was ok except for the HVAC furnace. The HVAC guys haven't returned yet to set up the furnace for propane. The guy from Trico told me to call him when the HVAC guys finished and he would return for the final inspection. Back and forth and forth and back, the same nonsense we've been going through the entire time we've been building this ranch house.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment